Approximate bill of quantities vs approximate quantities cost plan
An approximate bill of quantities should not be confused with an approximate quantities cost plan. This article explains the differences between them.
An approximate bill of quantities can be used on projects where it is not possible to prepare a firm bill of quantities at the time of tendering. Generally, the design will be relatively complete, but there is either insufficient time or information to determine the exact quantities required and so a conventional bill of quantities cannot be prepared.
For more information, see Approximate bill of quantities.
An approximate quantities cost plan is part of the iterative cost planning process and is a development of the elemental cost plan. Unlike the elemental cost plan (in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects), the approximate quantities cost plan is a first attempt to measure defined quantities from drawings. In effect, it is a costed approximate bill of quantities.
For more information, see Approximate quantities cost plan.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.